4-01-2022 Standing Tall - First Trusses and Electrical Panel Installed

This week we made the most visible progress to date.  First, the trench to the street for the electrical conduits were inspected and backfilled. The transformer pad was placed and compaction test performed and passed. This also cleared the path the real driveway will take. Next, the power panel was placed and temporary breakers and outlets installed. 

Meanwhile, the building construction was started. First, half the roof trusses and purlins were constructed on the ground. Next, the side columns were bolted upright, and finally a crane was brought in to hoist the preconstruction roof assemblies in place. 

Transformer Pad, Apr 2022
Transformer Pad
Power Panel, Apr 2022
Power Panel
Standing Tall, Apr 2022
Standing Tall

 