2-05-2023 Masonry Done, Cabinets In, Painting Done

It was a banner week. The cabinets were mostly installed, the painting is 98% complete (touch up needed in the future) and the masonry was completed. All of these milestones give us a feeling that there is light at the end of the tunnel. Most of the HVAC mini-split head units are installed. Next up, kitchen and bath tile, and granite counter tops.  Masonry Done Kitchen Cabinets  ...

Continue reading...

Sunday, February 19 2023

2-19-2023 Stairs, Railing, Driveway

Last week the floating stairs and railing were partially installed. There is a bit more left to do. And the ground dried out enough that the crew was able to build the driveway and fire turnaround. The drive is constructed of road base, that will compact down to a firm surface free from mud.  Stairs and Rails Driveway Turnaround...