2-05-2023 Masonry Done, Cabinets In, Painting Done

It was a banner week. The cabinets were mostly installed, the painting is 98% complete (touch up needed in the future) and the masonry was completed. All of these milestones give us a feeling that there is light at the end of the tunnel. Most of the HVAC mini-split head units are installed. Next up, kitchen and bath tile, and granite counter tops. 

Masonry Done, Feb 2023
Masonry Done
Kitchen Cabinets, Feb 2023
Kitchen Cabinets

 