10-20-2022 Driveway Pad and More Electrical
By Permalink
-This week the driveway pad was poured, In addition, walkways were added to connect the pad to the front and back patios. Electrical rough-in is nearly complete with the sub-panel being installed, and power from the main to the sub-panel. Additionally, the wider garage door opener and springs were installed. Next week we anticipate a interior framing inspection then on to final insulation.