We got the CO last week, and moved the RV up here on Sunday. The PODs will arrive this week and we'll get them unloaded.
Here's a link to the time lapse video of the kitchen and floors getting finished.
Monday, March 20 2023
By
We got the CO last week, and moved the RV up here on Sunday. The PODs will arrive this week and we'll get them unloaded.
Here's a link to the time lapse video of the kitchen and floors getting finished.
Tuesday, March 14 2023
By
The Ram Board that has been protecting our floor over the past several months is being pulled up to reveal our finished conctrete floors. It's good to get rid of the dust and debris from all the drywall and construction work. The only remaining job to do before final inspection is to get our master shower floor grouted.
Saturday we hooked up our wash machine and tested it. During this we noticed water coming out under the trim in the laundry room. After our GC opened several holes we discovered that a nail had penetrated the hot water supply. It losened when we ran the hot water for the washer.
On a very positive note, we passed the blower door test. The technician said this is the tightest house he's ever tested in Nevada. The results were 1.39 ACH50 where a passing house is less than 5.0 ACH50.
The propane tank was delivered, installed and filled this week.
Sunday, March 5 2023
By
A lot has happened since the last post. Last week saw final plumbing, and electrical being put in. Toilets placed, switches and outlets in as well as all lighting fixtures. Also we had the microwave drawer, range and refrigerator put in. We think this week we can get a certificate of occupancy by week end.
Sunday, February 19 2023
By
Last week the floating stairs and railing were partially installed. There is a bit more left to do. And the ground dried out enough that the crew was able to build the driveway and fire turnaround. The drive is constructed of road base, that will compact down to a firm surface free from mud.
Sunday, February 5 2023
By
It was a banner week. The cabinets were mostly installed, the painting is 98% complete (touch up needed in the future) and the masonry was completed. All of these milestones give us a feeling that there is light at the end of the tunnel. Most of the HVAC mini-split head units are installed. Next up, kitchen and bath tile, and granite counter tops.
Sunday, January 29 2023
By
The interior painting is nearly done. The doors need to be painted and there are touch up areas. We love the colors we picked: the trim and ceiling is Swiss Coffee, while the walls are Drift of Mist. Drift of mist is interesting in that depending on the light and the room can look light gray, or slghtly beige, and even sometimes a hint of sage, The contrast of the walls and ceiling are very nice.
The masonry is about 75% complete. We really like how it is turning out also.
Sunday, January 15 2023
By
The water softener was installed early in the week. We wanted it in before any fixtures and appliances get installed. Since we have high iron, manganese, and hardness we opted for a "green sand" filter for the iron and manganese and a conventional salt softener for the hardness.
The paint prep has been ongoing this week with all of the trim getting puitty and sanded, and the front two rooms are mostly prepped for paint. First the primer coat goes on then the ceiling and walls.
The snow has delayed progress on the outside for now.
Monday, January 2 2023
By
We were surprised that this last week our well was finally hooked up to the house and to the corresponding well pump controller. The pump is a variable speed (variable frequency drive or VFD) that keeps the water pressure a near-constant 60 psi.
In addition to the interior doors being installed and most of the trim, shelves were installed that covers up the last of the steel frame - chord bracing.
This week we had a large storm blow through dropping two inches of rain and 7 inches of snow in a 48 hour period.
Monday, December 26 2022
By
All of our interior doors are installed, and the door and baseboard trim is being installed. We're hoping that painting can begin later this week.
Monday, December 19 2022
By
All the interior wall texture has been completed letting us move on to the next phase: Doors, Trim and Paint! We chose the paint we're going to use (more on that later). The front porch and soffit are almost all complete, just waiting on the masonry to be applied. The remainder of the stairs and rail shipment were received this week completing the order, ready for installation after paint.
Sunday, December 11 2022
By
This week the drywall was completed and the mud and taping was completed. Starting yesterday, the guys started the wall texture. We picked an "Old World" texture which features some voids for character with smooth walls. These guys are amazing and super hard workers. Saturday they put in 13 hours from 5:30AM to 6:30 PM. Meanwhile, the front patio soffit is getting completed and should be done this week. This allowed our carpenters to star wrapping the columns for subsequent masonary application -- the engineered stone was purchased several months ago. Finally, part of our stairs and railing arrived. We are missing three skids containing the remainder of the treads, landing, and railing posts. More on this later.
Saturday, November 26 2022
By
Time lapse of the last couple of months of interior work. Click on this photo to view the video:
Sunday, November 20 2022
By
We have finally reached the point where the drywall installation is beginning. We passed the shear wall inspection and immediately loaded in the drywall and our drywall installer began on Saturday. What a wonderful milestone. Meanwhile after receiving the water test results from the well water sample, we settled on a local water treatment supplier for an iron and softener treatment system. We've also settled on the remaining fans we are installing in the great room and upstairs -- we already have all the bedroom fans. More on that later.
Monday, November 14 2022
By
We have had our insulation inspection and are ready to move on to drywall installation. In preparation for that, we installed nearly 5,000 square feet of Ram Board throughout the entire downstairs concrete floor. We spent the entire weekend installing the Ram Board, but it was nice being up there after a light snow storm passed by. Incidently, I placed a min-max thermometer inside, and even though the night temperatures are in the low 20's, the interior hasn't yet gotten below 51 degrees.
Tuesday, November 8 2022
By
These last couple of weeks saw some accelerated progress. As the electrical rough in wiring was finishing up, we installed twelve high intensity 6000K color high bay LED lights in the garage/shop. These exceeded expectations and also are now dimmable. I was concerned that for normal use, the lighting would be too intense, so we installed wiring that added a 0-10v dimming control circuit. Our electrical contractor was ignorant of this control circuit, but they eventually figured it out.
We added more garage door controls, and heated up several outlets throughout the house to aid in interior construction.
And...we passed our interior framing inspection including plumbing and electrical rough in. It was a great milestone on the way to completion.
Finally, today began interior insulation. A lot of progress in a couple of days. We're into the home stretch with drywall and finishing cabinets/carpentry/counters.
Saturday, October 29 2022
By
This week the driveway pad was poured, In addition, walkways were added to connect the pad to the front and back patios. Electrical rough-in is nearly complete with the sub-panel being installed, and power from the main to the sub-panel. Additionally, the wider garage door opener and springs were installed. Next week we anticipate a interior framing inspection then on to final insulation.
Sub Panel
Saturday, October 15 2022
By
Sunday, October 2 2022
By
The last weeks have seen most of the plumbing has been topped out. We also had all the vents routed to a single roof penetration that is behind one of the cupolas. There are a few areas of work still. One garage door lifter was installed, making garage access for larger equipment easier. Finally, we had a night visitor trip the camera alarm.
Sunday, September 18 2022
By
All three trades were working this week. The HVAC guys had an opening so they started running refrigerant lines for the 9 head duel unit mini-split system we're putting in. The plumbers also started this week and have plumbed the vents to run up and ven out of one of the cupolas. On top of that the garage door guys installed both garage doors. We're hoping this accellerates the completion of the house.
Sunday, September 4 2022
By
« previous entries - page 1 of 4
Last comments